SWEETWATER COUNTY — The Sweetwater County Board of County Commissioners on Tuesday unanimously approved a $2.36 million funding plan for an HVAC upgrade at White Mountain Library, including a budget amendment that allocates $549,954 in impact funds to the project.
Chairman Keaton West, who works at Vaughn’s Plumbing and Heating, the contractor awarded the project, recused himself from the discussion.
The amendment will decrease the available balance in the impact tax fund and increase the building and improvement budget.
Sweetwater County Grants Manager Krisena Marchal told the board the county was awarded its full request of a mineral royalty grant in 2025 for the project. The grant requires a 50% cash match.
She said the project is a high priority because the library’s antiquated system is failing sooner than anticipated and cannot be addressed through phased replacement or repairs.
“Since the grant has been awarded, the project costs have unfortunately increased due to several factors,” Marchal said. “Scope modifications identified during design and engineering, the discovery of previously unknown asbestos and inflation.”
At the commissioners’ Oct. 6 meeting, the board awarded the bid to Vaughn’s Plumbing and Heating of Rock Springs for $2,221,450. The board directed a committee to recommend a funding plan. The project includes removing and replacing a boiler, condenser and associated controls.
The committee, which included acting Chairman Robb Slaughter, evaluated several funding options, including delaying other approved capital projects, using available reserves and using other eligible county funds. Marchal said the committee also consulted the State Loan and Investment Board, which confirmed that costs incurred during the project could not be reimbursed retroactively through future grants.
The impact funds are available from industrial siting projects that predate specific designated uses. The budget amendment is required only to allocate the $549,954 in impact funds to the project.
According to the agreement with the county, Vaughn’s must substantially complete the work by April 30, 2027, with final completion due June 1, 2027. The contractor would owe $1,500 per day in damages for missing the substantial completion deadline.
Commissioner Taylor Jones said only one bid was received despite efforts to encourage more bidders.