ROCK SPRINGS – The Bureau of Land Management provided a schedule for the Resource Management Plan revision as discussed which was discussed on Tuesday.
The bolded items were or will be opportunities for public comment. The BLM is not seeking comments on the checkerboard removal since the decision record has already been issued.
Schedule
August 16-September 27, 2013 Extended scoping on Wild Horse Management (past)Â Â
Early-2015
Alternatives Formulation (delayed pending release of Wyoming Greater Sage-Grouse Record of Decision)
Mid-2015
Alternatives analysis
Early-2016
Draft RMP revision/Draft EIS
Mid-2017
Proposed RMP revision/Final EIS
Late-2017
Record of Decision